Lots to show you this week - the building site is starting to look more like a house now.
The rails on the landing have now been finished. The decorator has done an undercoat to protect the woodwork and it is now looking great.
Upstairs the plastering is virtually complete. We still have to wait to complete the main bedroom for some of the external works to be installed.
The doors upstairs have now been fitted and these are looking really good.
Even the short airing cupboard door looks good! The bottom of the door was removed and then the door cut to size before the bottom was refitted. They've done a great job!
The secret cupboards in the girl's rooms are taking shape (even with the boxing all around the waste pipes from the bathroom.)
The cupboards are perfectly sized for Emma!
The tiling in the girls bathroom is now complete. The wood effect floor tiles look really good and give the room a nice look.
I especially like the white metro tiles with the grey grout.
The Minoli tiles look good in the guest ensuite. The tilers have done a good job here.
Meanwhile in the main bedroom the doors have been taken off again to fix the length. They were slightly too long when they were first installed and so would have rubbed the carpet.
Luckily Damien the window fitter was able to remake the door from to fit.
Richard has also now plastered the ceiling in the bedroom. He has done a good job of the curved roof and the curved wall.
Downstairs the utility is ready for plastering...
and the games room light wiring is now ready.
Next it's the front door to be fitted.... sometime int he next week.